CBL-LRA Collaboration

Operation Turbo Recruit (OTR) — Status Snapshot

Anchor: recruits’ first day = Monday, Sep 14, 2026  •  As of Thursday, Jul 23, 2026
New first dayMon, Sep 14, 2026  (moved from Sep 1)
ApplicationsReopen Mon, Jul 27 for 2 weeks — all candidates reapply
TestingIn-person digital assessment (not remote)
Portal & commsCBL-branded / owned; LRA = tech support to Sep 14
Days to first day
53
Calendar days to Sep 14
Expected completion
Sep 12
All pre-onboarding work (cascaded)
Buffer vs Sep 14
+2 days
Slack before the anchor — tight but positive
Milestones
10 / 6 / 0
🟢 on track · 🟠 at risk · 🔴 red
How to read this:  Target = the original planned date (doesn’t change).  Expected = current best estimate of when it will really happen.  Days late = Expected − Target (a “+” means behind plan).

Milestone status

#MilestoneOwnerTargetExpectedDays lateFlag
1Kickoff meeting heldCBL + LRAJul 6Jul 6on planDone
2Weekly sync — scope revised (Sep 14; portal approach)CBL + LRAJul 22Jul 22on planDone
3CBL provides cbl.org.lr subdomain (via CBL IT)CBLJul 24Jul 24on planOn Track
4CBL delivers final JDs & rubric amendmentsCBLJul 27Jul 27on planOn Track
5LRA builds & configures the application portalLRAJul 26Jul 27+1 dAt Risk
6Advertise reopening of applicationsCBL + LRAJul 27Jul 31+4 dAt Risk
7Application window open (portal live) — 2 weeksCBL + LRAAug 10Aug 11+1 dAt Risk
8LRA configures assessment & drafts questionsLRAAug 12Aug 12on planOn Track
9Develop scoring guidelines (incl. CBL amendments)LRAAug 12Aug 12on planOn Track
10Automated shortlisting of applicant poolLRAAug 18Aug 20+2 dAt Risk
11Pre-live validation of config & scoring; testing readinessLRA + CBLAug 24Aug 26+2 dAt Risk
12Digital assessment — in-person testingLRAAug 28Aug 30+2 dAt Risk
13Results compiled & shared with CBLLRASep 2Sep 2on planOn Track
14CBL interviews & final selectionCBLSep 9Sep 9on planOn Track
15Offer letters issued & accepted; onboarding prepCBLSep 12Sep 12on planOn Track
16Recruits’ first day (onboarding)CBLSep 14Sep 14on planOn Track
Near-term critical path — the portal. CBL’s provision of the cbl.org.lr subdomain (via CBL IT, needed by Jul 24) gates go-live; LRA’s portal must be live for the Jul 27 opening. Open item to add to the plan: because testing is in-person, a physical testing venue still needs to be booked and secured ahead of the late-August assessment.
Check-ins: Thursdays  ·  next: Thu, Jul 30, 2026
Scope: 20 Bank Examiners + 4 IT Examiners